Project Profile
- Project Location : New Jersey
- Client Industry : Contractor/ Consultant
- Owner Industry : Large Scale Remediation Project, NJ
- Gwtt Scope : Build, O&M
- Contract Value : $1.5M (Construction)
- Project Duration : 9 Months (Construction)
- Contaminants : Arsenic, VOCs
Key Project Details
- Construction of Perched groundwater treatment system for the removal of arsenic and VOCs
- Installed underground conveyance piping and electrical conduit from 20’ deep sumps to a new treatment building
- Oversaw the erection of a pre-engineered Butler-style structure 40’ wide by 65’ long and 22’ high
- Assumed full operations and maintenance (O&M) of the treatment system after successfully testing and commissioning
PROJECT CHALLENGES
- Confined space activities required additional planning, safety policies, and procedures
- Project structure was located on a small hill, requiring additional logistical scheduling and laydown space considerations
Project Narrative
GWTT was selected as part of the design/build team contracted to construct a perched groundwater remediation system for removal
of arsenic and VOCs, as part of a large-scale remediation project in New Jersey. GWTT was the general contractor for this project,
with a construction contract of $1.5M.
GWTT’s scope of work included confined space activities associated with installing the duplex pump systems in existing precast
sumps approximately 20’ deep. Each duplex sump was installed with a stainless-steel rail and guide system anchored to the interior
sump wall. GWTT completed the installation of underground conveyance piping and electrical conduit from the sumps to the new
building. In addition, GWTT oversaw the modification to the existing slab for footer installations and erection of the building.
GWTT installed all the process equipment, including the solids holding tanks, clarifier, chemical feed systems, multi-media filters,
sludge conditioning tank, filter press, low-profile air stripper, arsenic adsorbers, and liquid phase carbon adsorbers. After the
process equipment and main control panel were set, GWTT completed the installation of the interior process piping and electrical
conduit.
The treatment system is fully automated using a PLC system installed by GWTT. The PLC allows for remote access by the operator,
which results in a cost effective alternative related to alarm scenarios and system shutdowns during off hours. The GWTT
Field Services team provides a full-time technician responsible for daily operation of the system.