Project Profile
- Project Location : Massachusetts
- Client Industry : Subcontractor/ Consultant
- Owner Industry : Federal
- Gwtt Scope : Design & Build
- Contract Value : $3.2M
- Project Duration : 12 Months
- Contaminants : PFOA, PFOS
Key Project Details
- 500 GPM flow rate
- Treatment system was housed in a pre-engineered steel building
- Equipment included: pre-filtration equipment, 40k lb GACs, PLC control equipment, VFDs, and piping, fittings, and valves
- GWTT commissioned and started up the system
- GWTT excavated and constructed the project backwash lagoon
PROJECT CHALLENGES
- Rapid-response contract with accelerated project schedule
- Ongoing supply chain delays and disruption
- Limited laydown area for piping assembly
Project Narrative
GWTT was engaged by a federal contracting firm to design and construct a water treatment system to address multiple municipal drinking water wells near a large military installation that was impacted by PFAS contamination. GWTT was responsible for completing all civil (excavation for underground utilities and foundation, as well as electrical conduits), construction of foundation, pre-engineered metal building, and all electrical and control systems, as well as mechanical assembly for all system piping.
The pre-engineered steel building was erected over a customized structural concrete foundation. The 2,100-square-foot building housed four 40,000-pound Granular Activated Carbon (GAC) Absorbers. The new treatment plant was connected to the existing water distribution system using 8”, 10”, 12” and 16” ductile iron pipe, fittings and valves.
The treatment system processes water through four GACs and then through a UV disinfection system as the final step prior to discharge. The treatment system was designed and programmed to operate continuously utilizing a PLC and was outfitted with leak detection, pressure transmitters, pH analyzer, flow transmitter, and multiple level sensors. The system is controlled by a custom master control panel with a PLC, cellular telemetry, and VFDs for the transfer pumps. The system backwash water from the GAC system is discharged into a lined retention pond that flows into an adjacent infiltration gallery. This allows for all backwash filtrate to settle out prior to water percolating back into the groundwater system.
